Potters Gate CE Primary School

Farnham, Surrey

Project Details

Client
Surrey County Council

Project Manager
HCC County Council

Contractor
Osborne

Value
£2.7 million

Contract Period
45 weeks

Procurement Type
2 Stage Tender

Form of Contract
NEC Option A (D&B)

Efficiency savings
17.2%

CCS Score
40 / 50

Expansion from 1FE to 2FE, extension and refurbishment works with a new Reception front entrance combined with internal re-modelling has formed a more open and useable space for visitors, staff and pupils alike as well as a new smart face to the school. The Library has been relocated and extended and a new Music and Drama space now extends out of the front of the school linking to the existing hall to allow improved after school community use.

The new five classroom extension is linked to the existing two storey block to the South-East of the school. The classes face South onto the sports pitch and use a canopy to avoid solar gain and provide shelter. The large sliding doors provide excellent access to the field and facilitate improved outside learning.

An extended Food / Design and Technology building has now been constructed off the existing hall together with new toilets and storage intended for school and community use.

The existing Music and Drama room has been extended to link in with the existing Victorian building and been converted to Reception classrooms. The school kitchen was fully upgraded during the Summer holidays.

Key Challenges

  • Minimal disruption to school during term time.
  • Design & construction of new classrooms using existing building
  • Aligning & managing Client & User expectations within a challenging budget.

How these were delivered

  • Collaborative meetings to develop the design, review value engineered options
  • Close liaison with school to formulate the optimum workable programme for both school and contractor.
  • Application of previous experience and best practice of working on primary schools

“I would just like to say how fabulous I think the entire building project has been handled and it was an inspired idea to include the children at this exciting time.

My 7-year old is so excited about his new classroom. He hasn’t stopped talking about how lovely the new building is, especially the big glass windows looking onto the field. He thoroughly enjoyed his Construction day. You created minimal disturbance to the children and parents and felt like you were not even there.

Thanks once again and we look forward to celebrating the big reveal upon completion.”

Parent
Potters Gate Primary School

Lessons Learnt:

The Good

  • Completed on time and within budget
  • Efficient lean methods adopted for construction programming
  • Minimum disruption working around the constraints of an occupied school – no complaints

SAVE / iESE Benefits & How:

  • Early contractor involvement and collaboration with school
  • Resource efficiency savings across multiple schemes.
ContractGateway 2 PlanningGateway 3 Contract Agreement Variation
Cost£2.7m£2.7m0
Time45 weeks45 weeks0