New Addington Leisure Centre

London Borough of Croydon

Project Details

CLIENT: London Borough of Croydon

PROJECT MANAGER: Gleeds

ARCHITECT: GT3

CIVIL ENGINEER: Enginuiti

CONTRACTOR: Willmott Dixon

VALUE: £33.7 M

CONTRACT PERIOD: 82 Weeks

PROCUREMENT ROUTE: Two stage
open book design and build

FORM OF CONTRACT:
NEC 3 Option A

TARGETED APPRENTICES
2 Technical 4 Trade

BIM: Level 2

PROJECT CONSISTS OF:

• Willmott Dixon are transforming the western side of Central Parade in
New Addington to provide community spaces, state-of-the-art sports
facilities and eight new family homes.

  • The new flexible space features two multi-purpose halls, a cafe, meeting rooms, offices and dressing rooms, with an option of licence applications for booked events.
  • The development will provide high quality and modern leisure and community facilities acting as a significant upgrade to the current provision in the area. A row of eight family sized townhouses will provide an appropriate street frontage to Chertsey Crescent with dedicated car parking

THE LEISURE AND COMMUNITY FACILITIES WILL PROVIDE:

• Community Halls
• Community Cafe
• Six lane 25 m pool with spectator seating for up to 150 people
• Learner pool
• Wet changing village
• Large fitness gym incorporating a spin studio
• Dry change facilities
• Multipurpose studios (Fitness and community)
• Indoor four court sports hall with associated changing facilities
• Public realm upgrades

ContractGateway 2 Planning Gateway 3 Contract AgreementVariation
Cost£32m£33.7m£1.7m
Time120 weeks120 weeksNIL

Apprentices:  4
CCS Target Score:  40/50
Target Waste Diverted:  99%
Efficiency Saving: Target 12%

CONTACTS

Dawes, Framework Manager                                                   Erika Buckenham, Framework Coordinator
Guy.Dawes@Willmottdixon.co.uk                                         Erika.Buckenham@Willmottdixon.co.uk