St Nicholas Primary School

London Borough of Croydon

Project Details

CLIENT: London Borough of
Croydon

PROJECT MANAGER: LBC
ARCHITECT: HNW

CIVIL ENGINEER: Lyons O’Neill

CONTRACTOR: Willmott Dixon

VALUE: £22M

CONTRACT PERIOD: 115 Weeks

PROCUREMENT ROUTE: Two Stage
open book design and build

FORM OF CONTRACT: NEC

APPRENTICES EMPLOYED: 4

BIM: Level 2

THE PROJECT:
During preconstruction the customer changed the scope of the project
from an extension to the existing school to a new build four-storey, 4FE
SEN Primary School to be built alongside the existing school. The works
include demolition the existing school buildings after the new one is built
to allow for more outdoor playing areas and an ecology garden.
The new building has been designed to have a steel frame, precast
planks and stairs and will be cladded with GBrick. This building has
been a unique challenge for Willmott Dixon as the project started with
6 months’ worth of enabling works, which involved removing 8000 m3
of soil and chalk on over 1000 lorry loads to get down to our foundation
level. To keep the site safe we removed the vast amount of chalk from
site. A soil nailing system has been put in place to hold back the now 5m
high sheer face. The school is located on a challenging tight site and the
school is a live learning environment through out construction.
I have put some further information in bullet points below:

ADDED VALUE:
  • School visits planned. Children are coming to learn about the project,
    take part in sustainability activities and have a site walk around
  • WD donated £500 to the schools summer BBQ and set up a stand with artist impression drawings depicting the new school building with the site team attending the event to answer any questions parents, pupils or teachers may have had.
ContractGateway 2 Planning Gateway 3 Contract Agreement Variation
Cost£21.9m£20.2m£300k
Time78 weeks78 weeksNIL

Apprentices:  5
CCS Target Score:  40/50
Target Waste Diverted:  99%
Efficiency Saving Target:  12%

Guy Dawes, Framework Manager
Guy.Dawes@Willmottdixon.co.uk

Erika Buckenham,
Framework Coordinator
Erika.Buckenham@Willmottdixon.co.uk

SCF website – www.scfsolutions.org.uk
Follow us on twitter – @SCFconstruct
Follow us on Linkin www.linkedin.com/
company/scfsolutions